VIKING gear pump It is a commonly used fluid conveying equipment, widely used in chemical, petroleum, fine chemical and other industries. VIKING is described in detail below Gear pump Installation and commissioning steps of.
1、 Installation preparation 1. Select the installation position: select a dry, ventilated and vibration free place to ensure the normal operation of the gear pump. 2. Preparation tools: including screwdriver, wrench, level gauge, etc.
2、 Install the gear pump 1. Install the base: first position the base at a suitable position, and then use a screwdriver and screws to fix the base on the ground. 2. Install the body: place the body of the gear pump on the base to ensure stable installation, and fasten the connecting bolts with a wrench. 3. Connect the inlet and outlet pipes: as required, connect the inlet and outlet pipes with the inlet and outlet flanges of the gear pump, and fasten them with a wrench. COLFAX agent
3、 Motor installation 1. Installation flange: install the motor flange on the motor side flange of the gear pump to ensure that the flange connection is tight. 2. Install the motor: place the motor at the installation position and fix it with screws as required.
4、 Electrical connection 1. Connect the power supply: connect the power line to the motor according to the requirements of the electrical drawing. 2. Grounding: To ensure safety, connect the grounding wire of the motor to the grounding wire.
5、 Lubrication and sealing 1. Add lubricating oil: according to the operating requirements of the gear pump, inject proper lubricating oil into the lubricating oil tank and ensure that the amount of lubricating oil meets the requirements. 2. Check the sealing: check the sealing elements of the gear pump to ensure the integrity and correct installation of the sealing elements to prevent leakage. CIRCOR SECCO
6、 Debugging 1. Starting motor: turn on the motor switch to start the motor. 2. Check the rotation direction: ensure that the rotation direction of the gear pump is consistent with the rotation direction of the motor. 3. Check the operation: observe the operation of the gear pump, and shut down for maintenance in case of any abnormality. 4. Adjust the outlet pressure: if it is necessary to adjust the outlet pressure, it can be achieved by adjusting the inlet and outlet valves. Viking
7、 Operation and maintenance 1. Regular inspection: regularly check whether the gear pump body, motor, flange connection and other parts are loose, worn or damaged. 2. Maintenance and lubrication: replace the lubricating oil regularly as required, and clean the lubricating oil tank and filter screen. 3. Handling of abnormalities: If abnormal sound, leakage, vibration, etc. are found, stop the machine for maintenance in time to ensure the normal operation of the gear pump.
Summary: Installation and commissioning steps of VIKING gear pump include installation preparation, installation of gear pump, motor installation, electrical connection, lubrication and sealing, commissioning and operation maintenance. Reasonable installation and commissioning steps can ensure the normal operation and service life of the gear pump. In order to ensure safety, the installation and commissioning shall be carried out in strict accordance with relevant specifications and requirements. ASL electrostatic oil filter