    VIKING gear pump It is a common centrifugal pump, widely used in chemical, petroleum, food, pharmaceutical and other industries. VIKING will be introduced in detail below Gear pump Installation and commissioning process of.

1、 Preparation before installation

Confirm the model, specification and technical parameters of the gear pump to ensure that it matches the process requirements.

Refer to the equipment layout drawing to determine the installation position of the gear pump. The place with good ventilation and easy operation and maintenance shall be selected as far as possible.

Check the integrity and packaging of the gear pump and its accessories to ensure that there is no damage or missing parts. COLFAX agent

Handle the connection of inlet and outlet pipelines to ensure that they are connected to the inlet and outlet pipelines of equipment.

2、 Installation process

Place the gear pump on a flat and level ground, and use a level gauge to adjust the levelness of the gear pump.

Install foundation bolts, and adjust the position and quantity of foundation bolts appropriately according to the size and requirements of the pump.

Connect the inlet and outlet flanges of the gear pump with the pipe flange, and fasten the flange with a wrench.

Check whether there is clearance between the gear pump and the pipeline. If there is clearance, adjust the connection between flanges. CIRCOR SECCO

Installation accessories, including inlet and outlet valves, safety valves, pressure gauges, etc. Pay attention to the installation position and direction of accessories.

Lubricate the gear pump to ensure that the lubricating oil or grease fills the gear chamber and the quality of the lubricating oil meets the requirements.

3、 Commissioning process

Open the inlet valve, check whether the inlet and outlet pipes of the gear pump have leakage, and if any, deal with it in time.

Start the motor of the gear pump, and judge whether the gear pump operates normally by observing the indication on the instrument and listening to the sound.

Check the pressure gauge of the gear pump to ensure that the indication of the pressure gauge is within the normal range. If the pressure is too high or too low, it needs to be adjusted accordingly.

Adjust the speed and running time of the gear pump according to the operating requirements of the equipment. Be careful not to exceed the rated operating parameters of the equipment.

Monitor the temperature and vibration of the gear pump to ensure that it is within the normal range. If the temperature is too high or the vibration is too large, it is necessary to timely check the causes and deal with them.

Conduct performance test to check whether the flow, head, efficiency and other parameters of the gear pump meet the requirements according to the requirements of the equipment.

4、 Precautions after installation and commissioning

Close the inlet valve of the gear pump, cut off the power supply, and carry out safety maintenance and routine maintenance.

Regularly check and clean the inlet filter and outlet filter of the gear pump to keep them unobstructed.

Regularly replace the lubricating oil or grease of the gear pump to ensure good lubrication effect. Viking

Regularly inspect the gear pump, check the wear of its bearings, seals and other parts, and replace the damaged parts in time.

Pay attention to the running status of the gear pump, and handle the abnormal conditions in time to avoid damage or accidents to the equipment.

In a word, the installation and commissioning process of VIKING gear pump needs to follow certain steps to ensure its normal operation and working effect. In the process of use, the equipment shall be regularly maintained according to the requirements of the equipment to extend its service life.


Recent browsing:

Related products

Related news

24-hour hotline

Tel.: 027-87775190

Tel.: 027-87775190 87775191 87775192

Address: B1216, Optics Valley International Building, 2-2 Guandongyuan Road, Hongshan District, Wuhan

Scan and contact us

Follow us for more highlights